PFEIFFER CANYON BIG SUR BRIDGE ON HIGHWAY 1

February 2017 had 1,150 percent of its normal February rainfall causing the bridge failure

pfeiffer 1

February 11 inspection found columns fracturing

pfeiffer 2

The Big Sur Pfeiffer Canyon Bridge had 2 of its 3 center support columns washed out in the heavy rains and a mud slide in the first week of February 2017. The columns started to fracture with the side load of the mud and Officials said the bridge was “damaged beyond repair” and declared a permanent closure in mid-February until the sagging and cracking structure could be replaced.

Caltrans closed the bridge late February

pfeiffer 3

There was no way to repair it so the original bridge was demolished by Golden State Bridge out of Benicia, Ca

Caltrans decision to demolish the bridge

pfeiffer 4

Demolition proved to be difficult